Review looks at whether activity detail, logic, constraints, calendars, resource assumptions and float treatment represent the proposed work. A discrepancy can come from modeling choices, incomplete information or error.
An analysis tests the schedule against the contract's requirements and against itself: whether the sequence is buildable, whether the critical path is credible, whether the durations reconcile with the proposed manpower, and what material assumptions or departures need clarification before acceptance.
Analyzing a baseline is not proofreading it. The submission will calculate, print and look orderly; the question is whether it describes the job the contract actually bought. That is answered by interrogating the things a tidy printout conceals, constraints, calendars, float and the logic underneath the bars.
Constraints can affect calculated dates, float and critical-path results. Analysts may consider their purpose, placement and effects in relation to the project, contract and selected analytical approach.
Working calendars, seasonal conditions, weather assumptions and exposed work may affect planned durations and the meaning of a schedule forecast. Their significance depends on the project facts, records and administration of schedule submissions and reviews.