Analyzing the fragnet in isolation
A fragnet should be reviewed in the schedule it was inserted into, including its logic ties and the status of that schedule.
General contractors, subcontractors and construction managers

For Developers, Owners & Public Entities
A time impact analysis represents inputs, assumptions and implementation choices. A review may examine how those choices relate to the project records, the administration of schedule submissions and the question posed.
A submitted impact analysis may be reviewed in relation to its selected schedule, modeled events, logic, durations, float assumptions and other information relevant to the assigned questions. Checks or re-performance depend on scope and available records; no particular starting schedule, finding or outcome is presumed.
The modeled relationships and their supporting information may affect calculated results. Their significance depends on the network, assumptions and the question being evaluated.

Possible assignment considerations
Evaluate the starting schedule and any adjustments against the purpose and time perspective of the analysis.
Assess whether the modeled activities and logic reflect what actually had to be done.
Check that the event is modeled as constraining work it genuinely constrained, rather than driving the completion date artificially.
Look for other events in the window, pre-existing slippage and concurrent causes the analysis does not address.
Considerations and limitations
A fragnet should be reviewed in the schedule it was inserted into, including its logic ties and the status of that schedule.
A submitted impact analysis may be reviewed in relation to its selected schedule, modeled events, logic, durations, float assumptions and other information relevant to the assigned questions. Checks or re-performance depend on scope and available records; no particular starting schedule, finding or outcome is presumed.
A general objection does not identify what is missing; the review points to specific logic, durations, dates or records.